Introduction
An Infrastructure Booking Authority (IBA) is used to tell Signallers about:
- using uncommissioned infrastructure, or
- infrastructure equipment that is:
- temporarily booked out of use, or
- decommissioned/permanently removed, or
- booked back into use, or
- commissioned.
Maintenance Representatives and Signallers use an NRF 003 Infrastructure Booking Authority form to jointly compile an IBA.
Compiling an Authority
Maintenance Representatives and Signallers
- Record details about the location of the infrastructure and the affected line.
- Record the type of infrastructure work to be listed in the IBA:
- use of uncommissioned infrastructure, or
- existing infrastructure temporarily booked out of use, or
- existing infrastructure decommissioned/permanently removed, or
- existing infrastructure booked back into use, or
- infrastructure installed.
- Record the equipment identification numbers. Give details about the equipment.
- If the work was advertised, record the date of the advertisement.
- If signalling equipment is to be bridged temporarily, record the Bridging Authority Number.
- Record the time and date, and the name of each representative, against the relevant discipline.
Completing an Authority if infrastructure is certified
Maintenance Representatives and Signallers
- Cross out No in the Certified column if infrastructure is to be certified fit for service on the existing IBA.
- Record the name of the representative of each discipline certifying the infrastructure, and the time and date, on the existing IBA.
- Strike through items that do not apply.
Completing an Authority if some infrastructure remains uncertified
Maintenance Representatives and Signallers
- Cross out Yes in the Certified column if infrastructure is not certified for return to service on the existing IBA.
- Compile a new IBA to detail infrastructure that is not being returned to service.
- Carry over the relevant date of advertisement to the new IBA.
- If signalling infrastructure is to continue to be bridged temporarily, record the Bridging Authority Number on the new IBA.
- Write the reference number of the new IBA against the corresponding infrastructure details on the existing IBA.
- Write the reference number of the existing IBA in the Reference IBA No. column, for uncertified infrastructure included in the new IBA.
- On the existing IBA, record the name of the representative of each discipline certifying the infrastructure, and the time and date.
- On the new IBA, record the name of the representative of each discipline certifying the infrastructure, and the time and date.